N46#85 Catco

Collection; Rochefort
Destination; Port Hueneme

View Video


N46#85 Time lapse from Nick Irving on Vimeo.

View Photos

 

N46#85N46#85N46#85N46#85N46#85N46#85N46#85

 

View Video

 


View Photos

 


Notes;

29th January 2019; ETA Port Hueneme 07th February

11th January 2019; Shipping information

Vessel – Theben
Shipping line – Wallenius Wilhelmsen
SCAC – WLWH
ETS Southampton – 15/01
ETA Port Heuneme – 10/02
BL number – GB1921537

10th January 2019; Arrived Southampton

10th January 2019; Replacement inverter received at office. Plan to take to boat 14th at lift out.

08th January 2019; Captain reports;

We have an issue with the mastervolt inverter,  not working. The generator is fine so I can still charge from the outlets. I have contacted Jean and spoke to Ronan David at Nautitech . We have an electrician arriving at 12.30. He will invoice Nautitech direct. Weather looks ok for early morning departure tomorrow.

07th January 2019; Stopped Port La Foret for weather. No problems reported.

06th January 2019; Departed France. ETA UK 10th January 2019

04th January 2019; Crew on board

19th November 2018; Planning to collect early January and  loading 15th January

23rd November 2018; Still no useful information re January sailings .  There are 2 voyages scheduled, but as yet they have not nominated the vessels I still don’t know if we would be able to load this boat on board.  Dates below for info.

16/01 – ETA 10/02
01/02 – ETA 26/02

23rd November 2018; Laura advises Bimini will be secured to deck for transport. see download

15th November 2018; Ex factory 11th December. Scott to do handover


Downloads

Download ; Bimini installation

Download ; Freight Booking Note

Download : Delivery quote

Download; Handover

Download; Bill of lading

 